The Elusive Tester to
Developer Ratio
printer-friendly
By
Randall W. Rice
One of
the most frequently asked questions I get is worded roughly:
"Can
you tell me what the industry standard tester to developer ratio is?"
My
answer is "No, because there is no way to get an accurate measurement
of such a ratio, especially across the IT industry where some
organizations perform no independent testing at all."
However,
I dislike simply dismissing the question because I think there is a
more important underlying question of:
"Can
you please tell me a quick and easy way to determine the correct number
of testers based on the number of developers?"
Once
again, the answer is "No, because there is more to determining the
number of testers than simply basing it on the number of developers."
There
are more accurate and reliable ways to tell how many testers you need
for a particular project than just applying a ratio. In my experience,
basing workforce plans on ratios can be dangerous because by the time
you learn that you don't have enough people, it is often to late to
bring additional people to the testing effort. Or, conversely, you may
realize during testing that you have more people than you need, which
adds additional expense to the project. I haven't seen the latter
scenario occur nearly as much as I have the former.
The
Problem With Ratios as a Benchmark
Let it
be clearly understood that I don't completely discount the use of
ratios in planning if they are your ratios, based in your experience,
your technology and your organizational structure. What I do see as a
risk is when an organization takes another organization's ratios and
applies them to their project without regard to differences in
technology, process maturity, and skill levels.
A
Case Study
For
example, Company A is planning a test for a new system that is
developed in-house. They have just developed a new testing process and
have hired five new testers for the project. All of the testers have
less than two years experience in testing and less than five years
experience with the company. Company A has 15 developers using visual
development tools. Management has directed that each module be
independently tested. In planning the staffing levels, Company A
checked with a variety of sources and concluded that a workable tester
to developer ratio would be 1:3. After the test had been underway for
about 3 days, it became apparent that the testers would need to work
longer days to keep up with the output from developers.
One of
the companies that Company A contacted to get a benchmark was Company
B. Company B has had a testing process in place for three years and has
also invested in an automated test tool to handle the basic tests.
Also, the developers in Company B perform a high level of testing
before the software is released for independent testing. Company B
currently has a tester to developer ratio of 1:3, however three years
ago, they had one tester for every two developers.
In
comparing the characteristics of the two companies, it is easy to see
how one company's experience might not apply to another organization.
Why, then, is there such an interest in finding "the" ratio of testers
to developers? My theory is that people believe that finding a ratio
could:
- Provide
a sanity check for current staffing levels
- Justify
future staffing increases
- Provide
a quick way to estimate workload and staffing.
However,
there are at least two key problems with the search for "the" ratio of
testers to developers.
Problem
#1 - There is not a one-size-fits-all solution.
As we
saw in the example, each organization has its own mix of people,
processes, and tools. Even if there was an industry standard, it would
have to be a generic standard, which at best would be a starting point
for staffing estimates.
Problem
#2 - The "industry standard" sample size is small compared to the
actual number of organizations performing testing.
Even
with sample sizes of 1,000 organizations or more, the average ratio
could be misleading. Much depends on the industry category, geographic
location and accuracy of the information being reported. As we learned
in Year 2000 efforts, there simply are not enough companies that
measure what they do to get an across the board sampling. Since the
more mature IT organizations are the ones that measure projects, the
measurements are naturally skewed toward mature organizations.
In the
case of tester to developer ratios, the difficulty is not in measuring,
but rather in gathering the data and relating it in a way that yields
meaningful information.
Problem
#3 - A tester to developer ratio seems to assume that all work products
must be independently tested. Although it sounds like
good practice to independently test all work, actually this often
places a bottleneck in the overall software delivery process. There may
be cases, such as low-risk modules that can be tested and certified by
the development team.
Some
Research and What it Means
In an
effort to develop some findings concerning the tester to developer
ration, I took and informal survey at QAI's 20th Annual Software
Testing Conference in September of 2000. Here are my findings:
- There
were 29 respondents
- The
minimum ratio was 0 testers to 1 developer
- The
maximum ratio was 1 tester to 30 developers
- The
most common ratio was 1 tester to 3 developers
- The
average ratio was 1 tester to 7 developers
- The
median ratio was 1 tester to 5 developers
The
above chart shows that the ratio of 1 tester to 3 developers was the
most common ratio reported. The majority of responses were at 1:7 or
below.
Observations
and Analysis
This was
not a scientific survey and the sample size was very small. In
addition, there is no way to judge factors such as process, industry,
people and tools. Realizing these limitations, the results showed that
many organizations fall at the lower end of the ratio range. There is a
commonly used informal benchmark of 1 tester to 3 developers which has
been discussed for awhile. These findings seem to reflect that 1:3 is a
popular ratio. An interesting correlation would be to relate the tester
to developer ratio with defect removal efficiency percentages, or with
Capability Maturity Model (CMM) levels.
A
Better Way
One of
my frequent observations about the ways testing efforts are estimated
is that too often the estimate is made before the scope of testing is
determined. This observation applies not only to people-hours, but to
overall time windows and human resources.
Determine
the Scope More Accurately
One
reason the testing effort is often estimated incorrectly is that the
estimate is not based on measurable items, such as test cases, testable
requirements, or testable transactions. I sometimes refer to this as
the "two, four, six, eight rule", where the time allocated to testing
is two, four, six or eight weeks, depending on what sounds good on the
day the project plan is finalized.
The
single best thing that could be done in estimating the testing effort
is to base it on a defined scope.
If
requirements are defined early in the project, there is a basis for
determining the scope of testing. At the minimum, test objectives
should relate to project objectives. At the time the project schedule
and statement of work are defined, there should be enough information
to estimate testing activities if functions are defined at a
quantifiable level. Testable requirements are a way to estimate tests
at a detailed level. However, care must be taken to estimate all phases
and types of testing required for testing a particular requirement,
plus the time to plan and evaluate the test, plus the time to repeat
the test ? several times if necessary.
Determine
the Test Team Size Based on Management Capability
I often
ask people, "What is the tester to developer ratio indicates you need
50 testers? Could you manage them? Could you get the funding to hire
them? Could you even find 50 testers to hire? If not, could you train
50 testers?"
There is
a practical limit at which you must look at time, cost and people and
make a reasoned judgment to achieve a workable balance.
To this
end, I often advise people to:
- Think
about how many people they can effectively manage,
- Look
at the scope of testing to see how much work will need to be performed,
- Assess
the testing process to see if too much work is being shifted to testers,
- Modify
the testing process, if necessary,
- Investigate
the role of automated testing in their organization,
- Consider
the phase and type of testing to be performed. Some types of testing,
such as usability testing can often be performed by small groups of
people.
After
analyzing the above items, a reasoned judgment can be made to staff a
team that is the right size to get the job done - no matter how many
developers you have.
Prioritize
the Testing Effort
Another
way to balance the testing workload is to prioritize the modules or
areas of the system to be tested. It is possible to quantify testing
based on risk, which is a function of the likelihood of failure and the
impact of failure. Not only can you prioritize the testing in terms of
the order of testing, but you can also adjust the types and extent of
testing by risk.
The fact
is, even if you had all the time in the world, you still would not be
able to test your software completely. Therefore, a line must be drawn
somewhere to get the most work possible into the planned time frames.
Perform
Contingency Planning
The
project manager and test manager should work together to plan early in
the project what can give if the deadline arrives and the product is
not ready to release, either due to defects or incomplete testing.
There are basically four areas that can be manipulated to meet an
overall implementation goal. These areas are:
- Scope
- perhaps some of the lesser-used functionality can be
implemented in a later release.
- Schedule
- perhaps the implementation deadline can be
extended.
- Cost
- Perhaps additional people can be added to the project to get more
work done in the planned timeframes. However, there is a danger of
violating Brook's Law: "Adding more people to a project that is already
late will make it even later."
- Quality
- perhaps certain types of testing could be
minimized. However, this is also a risky choice.
Conclusion
At Rice
Consulting Services, we will continue to research the question of
tester to developer ratios to learn if there really is a magic number,
although to date we see many risks in just applying a ratio. At best,
the most commonly mentioned ratio of one tester to three developers can
be used as a starting point for your staffing estimates. I advise
people to base staffing estimates in their own history, processes,
tools and skill levels and then use industry ratios (if you can find
and trust them) as a validation.
If
you would like to contribute to this research with your own tester to
developer ratio, just go to the research section on this web site. I
also welcome hearing about your experience in staffing the testing
effort in your company. You can e-mail me from the contact
page.
All materials on this site
copyright 1996 - 2008, Rice Consulting Services, Inc.
Rice
Consulting Services, Inc.
P.O. Box 892003
Oklahoma City, OK 73189
405-691-8075
"Leaders
are made, they are not born. They are made by hard effort,
which is the price which all of us must pay to achieve any goal that is
worthwhile." -- Vince Lombardi